menu.gif

Hydrant Flushing Update

(updated 4/2/2011 at 11:38 am)

We are flushing hydrants slowly to minimize discoloration. 

Tonight we well begin flushing the north end of the village (days 5 & 6) below.

 

Due to freezing temperatures 2011 Spring Hydrant Flushing was delayed until Easter Sunday, April 24th and did NOT begin on March 27th as previously stated.

Please continue to check this site for updates.

Typically, hydrant flushing takes about 10 days to complete and our department will be working

between the hours of 10:00 pm and 6:00 am.

Listed below are the targeted dates & locations. 

Please note that due to variations in hydrant flow, these dates are approximate. In order to ensure this program is a success, some hydrants may take longer to flush.

Please continue to check this site to see if there have been changes made to the schedule or call the Water Department at 265-3770 ext 5.

Due to this hydrant flushing some of our residents may experience a temporary discoloration in their water even if the hydrants in your area were not flushed out the night before.

Your water will remain bacteriologically safe for normal uses and consumption. 

If you should happen to experience discoloration in your water, open the cold water faucet and let the water run for a few minutes and it should clear up.  If your water should remain discolored, or if you should experience any other problems, please contact the Water Department during normal business hours at (585) 265-3770 ext 5. 

After hours or on weekends, please call (585) 265-3770 ext 30.

 

Day 1 & 2
Tentative Schedule
Bay Road to Ridge Road
Colorado Drive
Dewitt Road From Wellfield South to End
Inspiration Point Road
Joran Drive
Norwood Circle
Ridge Road East from Bay to Five Mile Line
Volk Road

 

 

 

Day 3& 4
Tentative Schedule
ABVI Goodwill - Webster Commons Blvd.  
Barrett Drive
Corning Park
Holt Road South of Route 104
Iroquois Street 
Main Street West of South Ave
Mohawk Street
Pierce Street
Pontiac Street
Ridge Road from five Mile Line Road to Village Line
Sanford Street
Seneca Street
Sherwood Ave
Wood Street
Day 5 & 6

Tentative Schedule

Ashwood Drive
Orchard St from Holt to Phillips Rd
Baker Street
Carriage Path
Commercial Street
Daniel Drive
Dean Spring Dr
Donovan Street
East Main Street
Holiday Inn Express
Kircher Park
Kittelberger Park 
Linda Lane
Lyons Drive
Martin Street
May Street 
North Ave
Scenic Village 
Railroad Street to 1st Hydrant
Reynolds Road 
Walnut Circle
Woodstone Circle

 

Day 7 & 8
Tentative Schedule
Clover Drive
Curtice Park
Dunning Avenue
Elm Street
Fuller Avenue from South Ave to Curtice Park
Gordon Park
Hawley Drive
Kathrene Court
Lapham Park
Lincolnshire Road
Maryvale Drive
Meadow Drive
South Avenue
Southwick Drive
Spry School
State Road Recreation Field

 

Day 9 & 10
Tentative Schedule
Champion Avenue
Cobb Street
Country Manor
Foster Drive
Harmon St.
Harmon Street & Curtice Park
Heartland Estates
Hefner Drive
Judson Street
Kent Drive
Kreiger Road 
London Road
Phillips Road North of Orchard
Transmission Main to State Road Tank

           

June 2011
S M T W T F S
29 30 31 1 2 3 4
5 6 7 8 9 10 11
12 13 14 15 16 17 18
19 20 21 22 23 24 25
26 27 28 29 30 1 2
3 4 5 6 7 8 9